# 六所域名解析项目交付设备上架
|
||
|
||
| ID | Creation Date | Assignee | Status |
|
||
|----|----------------|----------|--------|
|
||
| OMPUB-797 | 2023-02-07T17:21:17.000+0800 | 牛翔 | 完成 |
|
||
|
||
|
||
---
|
||
|
||
交付两台服务器:
|
||
* 流量接入解析服务器,按照TSG X Mark I进行安装
|
||
* 图谱绘制服务器,按照OLAP服务器进行安装
|
||
|
||
完成时间本周三(2023-2-8)**niuxiang** commented on *2023-02-08T11:32:07.087+0800*:
|
||
|
||
目前进度,两台服务器Raid卡有问题,已经联系厂家到现场处理。OLAP服务器操作系统已经在SSD安装完成,数据盘待处理。
|
||
|
||
|
||
|
||
---
|
||
|
||
**niuxiang** commented on *2023-02-13T17:14:05.815+0800*:
|
||
|
||
今日,已到六所进行设备上架、网络布线,目前测试环境已经正常运行
|
||
|
||
|
||
|
||
---
|
||
|
||
**niuxiang** commented on *2023-02-17T09:54:16.399+0800*:
|
||
|
||
20230215(周三),已完成六所设备交付,并将测试仪表取回公司
|
||
|
||
|
||
|
||
---
|
||
|
||
**zhengchao** commented on *2023-02-21T17:34:20.228+0800*:
|
||
|
||
👍
|
||
|
||
|
||
|
||
---
|
||
|
||
|
||
|
||