# 3楼至5楼机房实施
|
|
|
|
|
|
|
|
|
|
|
|
| ID | Creation Date | Assignee | Status |
|
|
|
|
|
|
|----|----------------|----------|--------|
|
|
|
|
|
|
| OSS-144 | 2020-07-14T15:37:17.000+0800 | 张硕 | 完成 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
---
|
|
|
|
|
|
|
|
|
|
|
|
3层机房搬迁至5层机房施工
|
|
|
|
|
|
|
|
|
|
|
|
Geedge办公区包含:
|
|
|
|
|
|
|
|
|
|
|
|
光纤统计、网线统计、新增工位查线、服务器交换机布线、跳线架布线、工位交换机布线、网络改造及交换机配置、radius认证系统上线、飞塔服务端+AP配置实施、机柜位置改造、桥架安装、机房空调安装、楼间光纤布线。
|
|
|
|
|
|
|
|
|
|
|
|
哈工大办公区包含:
|
|
|
|
|
|
|
|
|
|
|
|
机柜安装、新增工位查线、楼间光纤布线、工位交换机安装布线、飞塔服务端+AP配置安装、3楼与5楼交换机配置。
|
|
|
|
|
|
|
|
|
|
|
|
**zhangshuo** commented on *2020-07-14T17:14:17.352+0800*:
|
|
|
|
|
|
|
|
|
|
|
|
[~chenglei] [~jiaojianzhi] [~jianghuihui] [~yinfutao] [~wangyu] [~pengcheng] [~yangyang] 请及时更新任务进度及总结。
|
|
|
|
|
|
|
|
|
|
|
|
正是搬迁暂定本周六早10点进行。
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
---
|
|
|
|
|
|
|
|
|
|
|
|
**zhangshuo** commented on *2020-07-14T17:15:23.166+0800*:
|
|
|
|
|
|
|
|
|
|
|
|
机柜位置改造、桥架安装、机房空调安装 已完成。
|
|
|
|
|
|
|
|
|
|
|
|
网络拓扑已设计完成。
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
---
|
|
|
|
|
|
|
|
|
|
|
|
**zhangshuo** commented on *2020-07-16T14:03:57.213+0800*:
|
|
|
|
|
|
|
|
|
|
|
|
网络拓扑:IP段设计修改,整体连线未变。
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
---
|
|
|
|
|
|
|
|
|
|
|
|
**zhangshuo** commented on *2020-07-21T15:36:54.482+0800*:
|
|
|
|
|
|
|
|
|
|
|
|
计算两周后,把3层80M链路迁至5层,飞塔防火墙放置5层机房1机柜内,3层办公网络通过10G单模光纤连至5层核心SW
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
---
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|